 desks in customer service area
01 December 2009 |
 shelving in customer service storage room
01 December 2009 |
 tech support desks
01 December 2009 |
 bathroom fixtures
01 December 2009 |
 continuing studs continue over original brickwork
02 December 2009 |
 working on sink in customer service area
02 December 2009 |
 tech support operational
03 December 2009 |
 phone system in and working
03 December 2009 |
 LAN and Internet operational
03 December 2009 |
 finished counter space in customer service
03 December 2009 |
 mechanical room painted,
ceiling and lighting installed
03 December 2009 |
 water meter, distribution and cable ducts
03 December 2009 |
 finished boardroom
03 December 2009 |
 HVAC installation continues in new section
03 December 2009 |
 insullation started in new section
- this should be warmer now!
15 December 2009 |