desks in customer service area
01 December 2009 |
shelving in customer service storage room
01 December 2009 |
tech support desks
01 December 2009 |
bathroom fixtures
01 December 2009 |
continuing studs continue over original brickwork
02 December 2009 |
working on sink in customer service area
02 December 2009 |
tech support operational
03 December 2009 |
phone system in and working
03 December 2009 |
LAN and Internet operational
03 December 2009 |
finished counter space in customer service
03 December 2009 |
mechanical room painted,
ceiling and lighting installed
03 December 2009 |
water meter, distribution and cable ducts
03 December 2009 |
finished boardroom
03 December 2009 |
HVAC installation continues in new section
03 December 2009 |
insullation started in new section
- this should be warmer now!
15 December 2009 |