 discussing the next steps
23 November 2009 |
 garbage bin enclosure takes shape
24 November 2009 |
 exterior board completed
on main entrance side of building
25 November 2009 |
 carpeting underway
25 November 2009 |
 kitchen cabinets
25 November 2009 |
 pull outs for garbage and recycling
25 November 2009 |
 more kitchen cabinets
25 November 2009 |
 office carpeting
25 November 2009 |
 customer service drywalled, plastered and sanded
25 November 2009 |
 battery disconnect and UPS breakers
25 November 2009 |
 customer service area starting to get drywall
25 November 2009 |
 tech support with carpet and baseboard
25 November 2009 |
 more baseboard awaiting installation
25 November 2009 |
 window blinds installed
26 November 2009 |
 toilets and sinks await installation
26 November 2009 |